variation-claims

Variation Instructions – What can you claim for if you receive one?

The most frequent type of claim is probably those claiming for additional payment and/or an extension of time because of a variation. When making variation claims the objective is to demonstrate that an instruction, given by the Engineer, is a variation to the contract in the first place. If this can be established, it opens the door for evaluation of the additional payment and possibly to a further claim for an extension of time.

Engineer’s Instructions

In an ideal world, the Engineer would issue instructions to change the Works from those included in the contract and clearly identify such instructions as variations. Unfortunately, this is often not the case and the Contractor will frequently receive instructions via various methods which may or may not comprise variations. Instructions may be given by way of:

  1. Comments on the Contractor’s design drawings.
  2. Responses to requests for information.
  3. Comments on shop drawings.
  4. Comment on material approval requests.
  5. The issue of revised drawings.
  6. Instructions given by letter.
  7. Instructions given at meetings.
  8. Verbal instructions.

Many forms of contract require the Contractor to carry out such instructions. This raised the question as to whether the Contractor is entitled to additional payment or an extension of time as a result of such an instruction.

Remeasureable Contracts

On a remeasureable contract, the matter is simplified because the Works will be measured in their as-built condition, as instructed by the Engineer and evaluated using the contract rates and prices. This means that any changes made to the original contract will be included in the remeasurement, with a possible requirement to calculate new rates and prices if the specification has changed or new work items have been introduced. In this situation, a claim is not usually needed unless the changed work has affected the Time for Completion.

Lump-Sum Contracts

On a lump-sum contract, however, the contract usually allows the lump sum price to be adjusted for variations. Each variation must therefore be measured and valued to work out the amount to add to or deduct from the lump sum price. This is where the Contractor may need to submit a claim to show that an instruction is, in fact, a variation.

How a Variation Can Affect the Contractor

Variation instructions can affect the Contractor is several ways:

  1. Changes to the contract price. A variation usually requires the Contractor to carry out extra work or to raise the quality of the work. Sometimes the opposite happens, and the change results in a deduction from the contract price. Either way, on a lump sum contract, the variation must be measured and valued to establish the amount to add to or deduct from the contract price.
  2. Increased workload. A significant increase in work could affect the Time for Completion and lead to an extension of time claim. Remember here that the Contractor is not obliged to bring extra resources to the project or work extra hours to carry out the additional work.
  3. Late instructions. The timing of a variation could delay the time for completion. For example, if an instruction requires procurement of materials, plant or equipment that are on a long lead time and the instruction is issued towards the end of the project. Again, this would entitle the Contractor to an extension of time.

Consider Prolongation Costs

If an extension of time is warranted, the Contractor will be entitled to the payment of prolongation costs to compensate them for the additional site and head office overheads that they have been obliged to provide for the extended period. Payment of such costs would be in addition to the payment for the additional or changed work.

Learn more about variations and how to manage claims successfully via one of our practical, tutor supported e-courses. 

‬ ‬