FIDIC 2017: What You Need to Know Now

It is now 5 years since the FIDIC 2017 editions of the Red, Yellow and Silver Books were published. As anticipated, it’s taking the industry some time to get on board and adopt these latest editions on projects.

Change Can Be Uncomfortable....But it's Inevitable

Nobody likes change. Employers and engineers are no different. It can be uncomfortable and it takes time and effort to take effect. But, as time moves on more and more projects will move to the FIDIC 2017 editions and it's critical that project teams understand these contracts.

I also suspect that some engineers will resist the new contracts and will not recommend them to Employers. Why? Because the Engineer now has more obligations. There are also many provisions which provide consequences for the Engineer if they do not comply with their obligations.

Nevertheless, change is inevitable. This means that those involved in project management and contract administration need to know what changes were introduced in 2017 to ensure effective administration and most importantly, to ensure that parties meet their obligations.

Changes Summarised:

The following is a summary of the changes made in the 2017 Editions:

  • The Red Book now has 106 pages of General Conditions as opposed to the 1999 Edition, which had 62 pages. The Yellow and Silver books are similarly increased. The increased volume is said to be to bring greater clarity and include more procedures to be followed as a matter of contract.
  • The word “Claim” is defined as ‘a request or assertion by either Party to the other Party for an entitlement of relief under any Clause of these Conditions or otherwise in connection with, or arising out of, the Contract or the execution of the Works.
  • There is a provision to include a percentage in the Contract Data (formerly the Appendix to Tender) for profit and if no percentage is stated, the percentage shall be 5%.
  • The term “No-objection” is introduced and defined.
  • “Notice” is defined as ‘a written communication identified as a Notice and issued in accordance with Sub-Clause 1.3 (Notices and Other Communications)’.
  • There are many more requirements for the parties to submit Notices.
  • A Notice of Dissatisfaction may be issued by either Party if dissatisfied with an Engineer’s determination.
  • There are more detailed requirements for the Contractor’s Programmes, including programmes to show actual progress.
  • A provision is included for including rules and procedures to deal with concurrent delay.
  • Advance warning provisions have been included.
  • The procedures for evaluating and agreeing Variations are more prescriptive.
  • The type of events previously included under Employer’s Risks and Force Majeure clauses have been consolidated into a single clause – Exceptional Events.
  • Both Employer’s and Contractor’s Claims are now dealt with under Clause 20 (Employer’s and Contractor’s Claims).
  • The provisions of dealing with disputes are separated into a new Clause 21 (Disputes and Arbitration) to reflect the fact that claims only become disputes if a Party gives a Notice of a dispute.
  • Specific provisions of the requirements of a claim submission are included under Sub-Clause 20.2.4 (Fully detailed Claim).
  • Under Sub-Clause 20.2.4 (Fully detailed Claim), the claim submission period is extended from 42 days to 84 days, but submission is now a condition precedent to entitlement.
  • Under Sub-Clause 3.7 (Agreement or Determination), if the Engineer does not give Notice of agreement of rejection of a claim within 42 days, the Engineer shall be deemed to have given a Notice rejecting the claim.
  • The Dispute Adjudication Board (DAB) is now referred to as the Dispute Avoidance/Adjudication Board (DAAB). This reflects enhanced requirements for the DAAB to be proactive in dispute avoidance.
  • All DAABs are standing boards.
  • There are many more ‘deeming’ provisions whereby if a Party does not act in accordance with an obligation, then the provisions will state that a specific action is deemed to have taken place.

More Work?

From this, you may think that the new forms of contract require substantially more contract administration than in 1999. But in my opinion, this is not really the case. If we look at Arcadis and HKA’s annual reports on disputes in recent years, major causes of disputes are:

  1. Failure of the Parties to comply with their contractual obligations.
  2. Failure to administer the contract correctly.
  3. Lack of adequately trained and qualified contract administration staff.

This illustrates that project staff did not understand the contract and failed to administer it as FIDIC intended in 1999. To try to address these failings, FIDIC 2017 has more prescriptive procedures. It also introduces more consequences for failing to carry out obligations. Consequently, the new editions do not require significantly more contract administration than the previous editions. Subject to the proviso - if the previous editions had been administered properly and efficiently.

Contractors, employers and engineers who think that they can continue to staff projects with inadequately trained and experienced staff will soon find out that they are mistaken. It will hurt them financially. This will be especially acute, if the companies on the other side of the fence have taken steps to ensure their staff understand the new editions.

The 2017 editions of FIDIC place much more emphasis on and have stricter requirements for notices. Our book on the subject provides a valuable guide. It is available in Kindle, paperback, and hardback from Amazon.

Want to learn more about FIDIC 2017 and the differences from the 1999 editions? Starting 12th October, join us for our NEW live online course - FIDIC 2017 vs 1999: What's Changed?  Sign up before 7th September to save 25%. 


The Difference Between Claim and Dispute Submissions - FIDIC Omissions

25 Tips to Help You Avoid Costly Claims and Disputes

Often people ask us, 'what are the key things we must do to avoid disputes and claims?'. Good news - we've compiled all of them into one handy document of top tips to avoid claims and disputes!
Read more


FIDIC 1999 Claims book

FIDIC 1999 Claims

A Guide to Claims for Extensions of Time and Additional Payment Under the Red, Yellow and Silver Books

A new book by Andy Hewitt, FICCP, FCIOB, FCICES, FQSi

Inadequately expressed claims are one of the most frequent reasons for time-consuming and costly disputes. Andy Hewitt’s latest book examines the FIDIC Red, Yellow and Silver Books. He takes a look at each clause that provides entitlement to make a claim for an extension of time and additional payment.

Andy explains in practical terms the interpretation and application of clauses. He also discusses FIDIC procedures for:

  • The giving of notices.
  • The submission of detailed particulars of the claim.
  • The Engineer’s responses and determinations.

Read more


FIDIC 2017 Notices

A guide to the requirements, content and composition of notices under the FIDIC 2017 Red, Yellow and Silver books

Some of the biggest mistakes that contractors make when it comes to claims under FIDIC 2017 relate to notices. Such failures include failure to:

  • Give notices when obliged to do so by the contract.
  • Give notices within the time frames specified in the contract.
  • Properly identify communications as notices.
  • Record the necessary information within notices.
  • Cite the contractual clause under which the notice is given.
  • Address and/or copy the notice to the correct party.
  • Deliver to the notice to the place specified in the contract.
  • Deliver to the notice by the means of communication specified in the contract.

Read more


Claims class student online training

Claims Class Helps Student Secure US$1 Million

This month I am going to allow myself to pat myself on the back, because of a success story from a recent Claims Class student.

A gentleman from an African country contacted me to discuss enrolling on one of our claims courses. He had found out about Claims Class after purchasing a copy of my Book FIDIC 1999 Notices. This is what he told me.

Read more


Lump Sum Cash Contract

What is Included in 'Lump Sum'?

A simple matter that often causes confusion is exactly what a lump-sum price includes.

Take a typical contract designed by the employer. The contractor is required under the contract to provide the works defined on the drawings and in the specification. In other words, the drawings show the extent and the configuration of the design. The specification describes the composition and quality of the work. Thus, it is clear that the lump-sum requires the contractor to provide whatever is included in the drawings and specification.

Read more


Construction contract FIDIC 2017 notice of claim

How Does FIDIC 2017 Affect Claims?

I guess like many of you, I have not had the opportunity to examine the 2017 editions of the FIDIC contracts in much detail, because as yet, I have not come across any projects that are using them. This situation will, however, gradually change. As it does, we will need to know what has changed and how it has changed. As such projects reach final account stage there will undoubtedly be claims to resolve and disputes to settle. I have recently been doing research for a forthcoming book, so thought it would be worthwhile to highlight the changes from a claims perspective.

Employer's Claims

Read more


FIDIC Notices

FIDIC 1999 Notices - Andy Hewitt's Latest Book

At the end of 2019 I was working with a contractor-client on several extension of time and additional cost claims. I needed to demonstrate that the contractor had complied with the contractual notice provisions in FIDIC.

This client had sent some notices. In most cases though, these didn’t comply with the contract requirements. In many cases they were completely meaningless as notices.

Read more


unforeseeable site conditions and force majeure - coronavirus

Coronavirus and Construction - Is the Contractor Entitled to Claim?

 

The global hot topic this month is definitely the coronavirus. It's affecting many construction projects.  Labour, materials, plant or equipment are coming from China (or other affected countries) and supply has been delayed. So what do you do if you're a contractor in this situation? Are you entitled to make a claim?

Well...it depends on your particular contract, but possibly.

I know that this is a bit of a lawyer’s answer, but it really does depend on several things. Let’s however, have a look at what the FIDIC Red and Yellow Books, 1999 Editions, have to say on the subject.Read more


FIDIC Amendments and The Golden Principles

We have all seen it. We receive what we assume is a FIDIC form of contract. But when we examine its contents or the Particular Conditions, we find it has been subject to amendments and changed considerably. FIDIC amendments we often see include:

  • Clauses struck out, usually those that give the contractor rights and remedies.
  • New clauses appear which are often punitive toward the contractor.
  • The remeasurable Red Book changes to a lump-sum contract.
  • Time-frames may have been reduced for the Contractor’s actions and extended. Alternatively, time-frames vanish altogether for the Engineer and Employer’s obligations.

Added to this, the changes and amendments are often poorly drafted and the final version contains ambiguities and conflicts.

So what we end up with is not what FIDIC intended. In short, it does not do what it says on the tin.

Employers and Engineer’s make these changes in an attempt toRead more