interim claims

Interim Claims

How To Deal With Them

One of our Claims Class students asked for some advice on interim claims. It is a topic that often crops up, so I thought that readers of this blog might also benefit from some practical advice.

The principles discussed here are appropriate to many forms of construction contracts. However, for the purpose of this article I shall use the 1999 FIDIC contracts as an example.

Sub-Clause 20.1 (Contractor’s Claims) obliges the Contractor to submit a fully detailed claim with supporting particulars. You must be submit this within 42 days or the event or circumstance giving rise to the claim. However, sometimes you may not be able to ascertain the final effects of a claim event within the 42-day period.

Sub-Clause 20.1 (Contractor’s Claims) deals with such eventualities as follows:

… If the event or circumstance giving rise to the claim has a continuing effect:
(a) this fully detailed claim shall be considered as interim,
(b) the Contractor shall send further interim claims at monthly intervals, giving the accumulated delay and/or amount claimed, and such further particulars as the Engineer may reasonably require, and
(c) the Contractor shall send a final claim within 28 days after the end of the effects resulting from the event or circumstance, or within such other period as may be proposed by the Contractor and approved by the Engineer.

Consequently, if you cannot ascertain the final effects of a claim, the Contractor must submit an interim claim within 42 days. Following this, you should continue to submit monthly interim claims until the final effects are determined.

Each interim claim should be based on the best information available at the time. Each update should be based on additional or more accurate information as it becomes available. The Contractor should submit a final claim within 28 days after the effects have ended.

This procedure ensures that the Engineer and Employer are kept updated. They will have access as to the latest estimates of time and costs to enable them to take appropriate action.

What should a claim include?

In practical terms we have three options when considering what information, the interim and final claims should contain:

  1. The first interim claim will contain the project details, the details of the cause of the claim, a demonstration of contractual entitlement, the latest available information and an interim calculation of the effect in terms of time and/or payment. Subsequent interim claims and the final claim will present information that has subsequently become available. It should include revised calculations of time and payment.
  2. As the above, but the final claim will consolidate everything into a stand-alone document. This one document will contain the complete particulars of the claim.
  3. Each claim submission will contain everything related to the matter that is available at the time of submission. Each will tell the whole story to date.

There are some key points for effective claims that we repeat time and time again on this blog. Firstly, the reviewer’s job should be made as easy and pleasant as possible. Secondly, that a claim should comprise a stand-alone document to enable the respondent to make a fully reasoned response. Therefore, when considering the advice above, it is clear the third option is the best one.

In practical terms, the man-hours to achieve the best and most professional submissions will be about the same as the “easy” options. So, when preparing interim claim on behalf of our contractor clients, our consultancy practice always prepares each submission as a stand-alone document. Our advice to you, would be to do the same.


FIDIC 2017 Notices

A guide to the requirements, content and composition of notices under the FIDIC Red, Yellow and Silver books

Some of the biggest mistakes that contractors make when it comes to claims relate to notices. Such failures include:

  • Failure to give notices when obliged to do so by the contract.
  • Failure to give notices within the time-frames specified in the contract.
  • Failure to properly identify communications as notices.
  • Failure to record the necessary information within notices.
  • Failure to cite the contractual clause under which the notice is given.
  • Failure to address and/or copy the notice to the correct party.
  • Failure to deliver to the notice to the place specified in the contract.
  • Failure to deliver to the notice by the means of communication specified in the contract.

Read more


Claims class student

Claims Class Helps Student Secure US$1 Million

This month I am going to allow myself to pat myself on the back, because of a success story from a recent Claims Class student.

A gentleman from an African country contacted me to discuss enrolling on one of our claims courses. He had found out about Claims Class after purchasing a copy of my Book FIDIC 1999 Notices. This is what he told me.

Read more


Lump Sum Cash Contract

What is Included in 'Lump Sum'?

A simple matter that often causes confusion is exactly what is included in a lump-sum price.

Take a typical contract designed by the employer. The contractor is required under the contract to provide the works defined on the drawings and in the specification. In other words, the drawings show the extent and the configuration of the design. The specification describes the composition and quality of the work. Thus, it is clear that the lump-sum requires the contractor to provide whatever is included in the drawings and specification.

Read more


The Difference Between Claim and Dispute Submissions - FIDIC Omissions

The Difference Between A Claim to the Engineer & A Claim in Arbitration?

A student recently asked, "is there any difference between a claim submitted to the Engineer and one submitted for arbitration?" My response was along the lines of “Yes, there frequently is, but there shouldn’t be”.

The Scenario:

Let me explain why by describing a very frequent scenario related to claims.

Read more


Variations and Preliminaries

Claims for Additional Preliminaries as a Result of Variations

Variations - something that comes up a lot in our courses. One question crops up time and time again. Does the contractor have entitlement to payment for additional preliminaries arising from variations?

The short answer to the question (as usual) is that it depends.

What Are Preliminaries?

Read more


construction 2020

Reflections on Construction in 2020

To say that 2020 has been an unusual year would be an understatement. Not just for the construction industry, but for all of us around the world. Despite the challenges, things are not entirely doom and gloom. We have all learned in one way or another from the COVID-19 experience. Sometimes we need a challenge to force us to think about alternative ways of doing things.

Read more


final account disputes

Why do Final Accounts lead to Disputes?

I recently provided advice on a dispute of US$250M. This sum includes variations, prolongation costs, acceleration costs, disruption costs and delay penalties. The dispute crystalised when the contractor submitted his final account. This is a familiar occurrence. In fact, a large proportion of disputes occur when the project is either nearing or after completion.

Read more


Construction contract FIDIC 2017 notice of claim

How Does FIDIC 2017 Affect Claims?

I guess like many of you, I have not had the opportunity to examine the 2017 editions of the FIDIC contracts in much detail, because as yet, I have not come across any projects that are using them. This situation will, however, gradually change. As it does, we will need to know what has changed and how it has changed. As such projects reach final account stage there will undoubtedly be claims to resolve and disputes to settle. I have recently been doing research for a forthcoming book, so thought it would be worthwhile to highlight the changes from a claims perspective.

Employer's Claims

Read more


Progress Updates – Fact or Fiction?

Contractors often shoot themselves in the foot when preparing progress updates for the employer’s team. Many times we see months worth of updates which present a rose-tinted view of project progress.

Whilst it is tempting to keep reporting good news month-on-month, be wary. A less than competent consultant may believe such reports because good news will not involve them in additional and troublesome work. However, you could be causing problems for yourself further down the line.

Problems frequently arise when the contractor needs to submit a claim for an extension of time. It becomes very difficult for him to subsequently tell the employer’s team: “I know we kept telling you that there was no delay to the completion date, but actually there is and it’s not our fault, so please can I have an extension of time.

Read more