can the engineer reject the contractor's programme? Construction Scheduling and Float

Can a FIDIC Engineer Reject the Contractor’s Programme?

One question that is often asked by students is “what actions can the FIDIC engineer take after reviewing the contractor’s initial programme?”. Many people think that the engineer may ‘reject’ the programme if he/she has reason to do so, but this is incorrect.

Let’s have a look at what Sub-Clause 8.3 (Programme) of the 2017 Edition of the Red Book has to say on the subject.

Firstly, it includes a lengthy list of requirements and inclusions that the programme should comply with. The detailed wording has been reduced here for clarity:

  • The programme shall be prepared using programming software stated in the specification.
  • The commencement date and the time for completion, of the works and of each section.
  • The date the contractor will be given right of access to and possession of the site.
  • The order in which the contractor intends to carry out the works.
  • The review periods for submissions.
  • The sequence and timing of inspections and tests.
  •  All activities, logically linked and showing the earliest and latest start and finish dates and the critical path.
  • The dates of days of rest and holiday periods.
  • Key delivery dates of plant and materials.
  • A supporting report which includes:
    • a description of all the major stages of the execution of the works
    • a general description of the methods which the contractor intends to adopt in the execution of the works
    • the contractor’s estimate of the number of personnel, and equipment required on the site.

Sub-Clause 8.3 (Programme) then goes on to deal with the engineer’s actions after receiving the programme for review:

The Engineer shall Review the initial programme… submitted by the Contractor and may give a Notice to the Contractor stating the extent to which it does not comply with the Contract …

To continue reading this article, please fill in the form below.