Extension of Time: what events give you grounds to claim?
Andy's Blog,Construction Claims
November 9, 2026
If your project has hit a delay, one of the first questions to answer is whether you’re entitled to an extension of time. Getting this right matters for two reasons: It removes the Employer’s right to claim delay damages…
Variation Instructions – What can you claim for if you receive one?
Andy's Blog,Construction Claims,Variations
October 14, 2026
The most frequent type of claim is probably those claiming for additional payment and/or an extension of time because of a variation. When making variation claims the objective is to demonstrate that an instruction, given by…
Additional Payment – Can you Claim When an Extension of Time Is Warranted?
September 16, 2026
In a recent article, I looked at the events that can give you grounds for an extension of time. This time, I want to look at what comes next: when an extension of time also gives you the right to claim additional payment,…
Claims & Responses: The Engineer’s Role in Stopping Disputes Before They Start
Construction Claims,Responses & Determinations
June 17, 2026
Claims and Responses: The Engineer's Role Every claim needs a response and, under most contracts, this responsibility falls to the Engineer. Under most common international contracts, the Engineer is required to review…
Termination and FIDIC: The 4 Key Clauses You Need to Know
May 19, 2026
Termination is a hot topic right now due to the current hostilities in the Gulf region. This article examines what the FIDIC contracts say on the subject, with a focus on the 4 key clauses you need to know and understand.…
How to Claim During Periods of Regional Hostility
March 18, 2026
I have received several enquiries from Claims Class students citing the current hostilities in the Arabian Gulf and asking whether the situation provides grounds to claim. The answer, as usual, is “it depends”. Firstly, in…
Notices of Claim and Civil Law
February 5, 2026
I recently read an interesting article by Joseph Durkin, Senior Vice President at Burford Capital. The article discusses notices, with a focus on the Saudi Arabian jurisdiction. This region is known for using FIDIC. And…
10 Point Strategy for Responding to a Claim
Andy's Blog,Construction Claims,Responses & Determinations
December 4, 2025
You are tasked with reviewing a claim, responding to it and hopefully, reaching agreement with the contractor. So, how do you go about it? Some forms of contract set out clear provisions that oblige the engineer to act…
How to Manage Delays and Change in Lump Sum Contracts
Construction Claims,Contract Administration,Delay Analysis
November 10, 2025
Lump sum contracts are one of the more common forms of agreements in the construction industry. They provide the client with a degree of price certainty, as the contractor agrees to complete the works for a single,…
10 Top Tips for Claim Presentation
October 7, 2025
You have established that a claimable event has occurred on your project. You have gathered the evidence and records, completed your delay analysis and/or calculations of the additional payment. You have decided on the…









