The Engineer's Responses and Determinations: What Should be Included?

Earlier this year I presented a CPD talk to RICS members in Dubai on the topic of Engineer’s Responses and Determinations. I usually like to kick things of with a poll and I asked the group the following questions:

How many people have experienced a situation where the Engineer does not respond to a claim within the contractual time-frame? Almost everyone confirmed that they had.

How many people have experienced a situation where the Engineer’s response has done little to resolve the claim? Again, almost everyone confirmed that they had.

How many people have experienced a situation where the Engineer’s response has caused the matter to escalate to a dispute? Over 50% of attendees confirmed that they had.

How many think that failures of the Engineer to carry out their contractual obligations on claims is helpful to projects? No one thought that this helped projects.

This is clear feedback from RICS members that the Engineers often do not perform their obligations. This has a detrimental effect on projects.

So, what should Engineers be doing to help projects when responding to claims? Well, as usual, the contract provides the answers, so let’s have a look at what the FIDIC Red Book has to say on the subject.Read more


Construction contract FIDIC 2017 notice of claim

How to Ensure you Avoid Costly and Time-Consuming Disputes on your Projects

We all want to avoid disputes on our construction projects. But it seems we fail to learn from lessons of the past. ARCADIS have just published their annual Global Construction Disputes Report 2019. It makes interesting, but, not altogether surprising reading.

This year, the top three reasons for disputes are:

  1. Owner/Contractor/Subcontractor failing to understand and/or comply with its contractual obligations;
  2. Errors and/or omissions in the contract document;
  3. Failure to properly administer the contract.

Some other interesting noteworthy observations are:Read more


Q&A: Delay Analysis

In partnership with the CIOB, Claims Class is running a series of monthly webinars on construction claims. The webinars cover some of the modules Construction Claims e-courses. In this webinar, we took a look at preparing a delay analysis.

At the end of each webinar, we invite questions and send the attendees answers to any questions that we do not have time to answer during the webinar. We've received good feedback from the two previous blogs on Q&A: Contract Administration and Q&A: Types of Claim.  So, I've decided to do the same for this month's blog. The following are questions and answers from the webinar on Delay Analysis.Read more


construction claims responses and determinations, changes in legislation

Q&A: Types of Construction Claims

In partnership with the CIOB, Claims Class is running a series of monthly webinars on construction claims. The webinars are a condensed version of our Construction Claims e-courses. This post includes questions around claims for variations, FIDIC 1999, prevention, changes in legislation, prolongation costs and a host of other topics.

At the end of each webinar, we invite questions and send the attendees answers to any questions that we do not have time to answer during the webinar. I thought that this would provide some useful insight to our blog readers. The following are questions and answers from the webinar on Types of Claim.Read more


Q&A: Contract Administration for Claims

In partnership with the CIOB, Claims Class is running a series of monthly webinars on construction claims. The webinars are based on our Construction Claims e-courses and workshops and have attracted between 150 and 300 attendees per session.

At the end of each webinar, we invite questions and send the attendees answers to any questions that we do not have time to answer during the webinar. I thought that this would provide some useful insight to our blog readers so, the following are questions and answers from the webinar on Contract Administration for Claims.Read more


How to Ensure a DAB is Formed Correctly

A blog subscriber recently asked for some advice on the setting up and organisation of a Dispute Adjudication Board (DAB). They specifically wanted to know what to do if one of the parties is trying to frustrate the procedure by refusing to agree to the appointment of the DAB. The following advice is relates to the FIDIC contracts. However, it may be equally applied to other forms of contract that have dispute board provisions.

Read more


Construction contract FIDIC 2017 notice of claim

Notices: Should a Contractor submit if he is not sure whether he intends to make a claim?

A Claims Class blog follower recently asked for advice on the correct interpretation of FIDIC Sub-Clause 20.1 (Contractor’s Claims).  What happens in situations where the Contractor is not sure if it will submit a claim or not - should they submit a notice of claim?

Often the Contractor becomes aware of an event that may cause delay, additional Cost or entitlement for additional payment. At that time, he may not be aware of the final effect of the event.
Read more


Time at Large - An Explanation

A blog reader asked for an explanation of “time at large”. This is not something that I have personally come across in practical terms. For the advice that I am about to give, I am indebted to my ex-boss, Roger Knowles. Roger provides an explanation in his book, 150 Contractual Problems and their Solutions. Roger explains it arises:

"when a contract is entered into with no period of time fixed for completion. Where this occurs, the contractor’s obligation is to compete within a reasonable time."

I have never experienced such a situation and I expect that when it does occur, it will be on Read more


Force Majeure

What Qualifies As Force Majeure Under FIDIC?

One of our blog subscribers requested advice on Force Majeure under the FIDIC Red or Yellow books. The good news is that Force Majeure clauses are similar under the Red, Yellow, Silver and Gold forms of FIDIC. Therefore, this applies to all of them.Read more


Delayed Issue of Drawings Or Instructions FIDIC

How To Ensure Engineer’s Responses And Instructions Do Not Result In Expensive Claims

A request came from one of our blog followers. It was to examine the Engineer’s duty to provide instructions and responses within a reasonable time. In my experience, failure of the Engineer to comply with such obligations often gives rise to claims. Delayed issue of drawings or instructions are a regular feature of projects around the world.

I shall use the 1999 FIDIC Red Book as an example, although other forms of contract also contain similar provisions.

Read more